Material Lead Times & Delays: Supply chain challenges continue to impact utilities across the United States and material lead times. As your trusted energy partner, we are committed to working with our customers and suppliers to minimize the effects of these longer lead times. We recommend that you factor the possibility of supplier delays into your project timeline. Transformers are ordered upon completion of engineering designs. Lead times can vary from 12-24 months.